How much does a septic permit cost in Wisconsin?
A sanitary permit for a new or replacement conventional septic system costs $350 to $575 in the seven Wisconsin counties below. A mound costs $450 to $1,283. Each figure comes from the county's posted fee schedule. Some amounts include a $100 state fee, as the Washington County and Sawyer County schedules note.
Last checked Nov. 2026
Sanitary permit fees by county
| County | Conventional | Mound | Holding tank | Renewal or transfer | Notes |
|---|---|---|---|---|---|
| Chippewa | $350 | $500 | $400 | $50 | Effective Jan. 1, 2026 |
| Dane | $509 | $1,283 | $509 | Not listed here | Effective Jan. 1, 2024. Designs up to 2,000 gpd. |
| Polk | $525 | $525 | $620 | $80 | Effective Jan. 1, 2026 |
| Sawyer | $450 | $450 | $450 | $100 renewal, $50 transfer | Effective Jan. 1, 2026. Includes $100 state fee. |
| St. Croix | $575 | $735 | $735 | $100 | Schedule dated April 28, 2026. Includes $100 state surcharge. |
| Washington | $500 | $700 | $600 | $50 | 2026-2027 schedule. Includes $100 state fee. |
| Waukesha | $551 | $1,167 | $869 | $170 | Under 3,000 gpd. No effective date on the page. |
Fees are as posted when last checked. Call the county before you budget. Counties not listed did not have a fee table we could open.
Other county fees
Some counties charge less for smaller jobs. Polk charges $200 for a reconnect, privy, composting or chemical toilet permit. Sawyer charges $150 for a privy and $100 for a reconnection.
Some counties charge for soil test review. Sawyer charges $50. St. Croix charges $35. Dane charges $227 for a soil test onsite inspection.
Some counties charge for plan review. Washington charges $150 for a county plan review of an at-grade, in-ground pressure or mound system. St. Croix charges $400 in place of a state plan review.
Dane County also bills a $12 yearly septic maintenance fee per system on the property tax bill.
What the permit does not cover
The permit is a small part of the cost of a new system. The soil tester, plumber, tank and installation are billed separately by the businesses you hire. No state agency publishes a standard price for that work.
Only a Wisconsin licensed plumber can apply for a sanitary permit. The plumber usually pays the fee and includes it in the bill.
See perc tests and soil evaluations and holding tank vs mound for what each system needs.
Sources
- Chippewa County 2026 fee schedule, effective January 1, 2026
- Public Health Madison and Dane County, Well and Septic Program Fee Schedule (December 2025)
- Polk County Land Information Fee Schedule, effective January 1, 2026
- Sawyer County Zoning Administration Fee Schedule, effective January 1, 2026
- St. Croix County Community Development fee schedule
- Washington County 2026-2027 Land Resources fee schedule
- Waukesha County Environmental Health Fee Schedule
- Sawyer County Sanitary Requirements (only licensed plumbers apply for permits)